 Post subject: Planning Worksheet
PostPosted: Thu Apr 19, 2012 9:23 pm 
Offline

Joined: Wed Apr 18, 2012 7:40 pm
Posts: 1
Country: Norway (no)
Hello

In Production the Planning Worksheet is used to plan purchases and requirements.

When I use the function Calculate Net Change Plan or Calculate Regenerate Plan, it creates several lines for SOME Items.
To show why generated; Safetystock, Critical, different Dates and so on.

For planning this is so far so good, but when I creating a PO (or transfer to Req Worksheet), it is still several lines per Item, but I'd like to have just one line per Item. Our Vendors do not see the point in a PO with many lines for same Item. ](*,)

We use NAV 5.0 SP1.

Suggestions appreciated.


Attachments:
File comment: First the lines/requirements are calculated
planning worksheet.jpg
planning worksheet.jpg [ 49.02 KiB | Viewed 333 times ]
File comment: Second, items (lines) transferred to PO
planning worksheet to PO.jpg
planning worksheet to PO.jpg [ 67.4 KiB | Viewed 333 times ]
File comment: Finally, created as several PO lines
PO lines.jpg
PO lines.jpg [ 23.59 KiB | Viewed 333 times ]
Top
 Profile E-mail  
 
 Post subject: Re: Planning Worksheet
PostPosted: Fri Apr 20, 2012 8:11 am 
Offline

Joined: Wed Apr 07, 2004 9:39 am
Posts: 338
Location: Bangalore
Country: India (in)
Hi Tek,

I have a doubt on the starting and ending dates of the lines shown on the planning worksheet. Did you try with sames dates on two lines with same item and vendor selected?

I may be a reason why, NAV is creating two POs because the expected receipt dates are different.

Chn


Top
 Profile E-mail WWW  
 
 Post subject: Re: Planning Worksheet
PostPosted: Fri Apr 20, 2012 1:01 pm 
Offline

Joined: Sat Apr 14, 2012 7:58 am
Posts: 17
Country: India (in)
Hi Tek,

Though they are same items, two different lines are created since the due dates are different for both the lines. Depending on the due date "expected receipt date" in purchase line is calculated. If you want to create only a single line in the Purchase Line even with the different due dates then you need to configure your re-ordering policy appropriately for that item (Goto Item card and select the planning tab).

Hope this helps.

_________________
Cheers,
Prashanth.


Top
 Profile E-mail  
 
 Post subject: Re: Planning Worksheet
PostPosted: Sun Apr 22, 2012 10:11 am 
Offline

Joined: Sun Feb 28, 2010 10:38 am
Posts: 11
Country: India (in)
Hi,

Check the Reordering Policy and ReOrder Cycle fields on the Item Card / SKU if applicable.

Regards,

Sridhar


Top
 Profile E-mail  
 
Display posts from previous:  Sort by  
Post new topic Reply to topic  [ 4 posts ] 

All times are UTC + 1 hour [ DST ]


Who is online

Users browsing this forum: absolutelyfreeweb, Google [Bot] and 18 guests


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum


Search for:
Jump to: