Has anyone used the Calculation base on ACTUAL OUTPUT? can anyone please explain the use of this option. What is the difference of the Two option,because I tried to use that but, I received no output from that option but when i select the expected output, it display a result. Hoping for your reply? Thanks

Answers

  • kapil4dynamicskapil4dynamics Member Posts: 591
    Yeah Actual is used after posting the output and expected is used before posting the output. Both of them use same calc factor i.e. from BOM line but it depends on if u have short output (means finished qty is less than the actual starting qty or more sometimes) then the qty using actual will vary.

    To check this create a prod order with qty 10 with RM = 1 per pc. Post the output for 6 qty and now calc consumption using both options u will get the answer.
    Kapil Khanna