Reservation in Production order in AX2009

mukshamuksha Member Posts: 274
edited 2013-03-06 in Dynamics AX
Dear Friends,

On of my customer is using multilevel BOMs. When we firm the production order, this creates the reservation and mark it for next level of production order. Customer wanted to use the Quality at each stage after production. When we wanted to move the output material of one production order to Rejection Warehouse system is giving error that No quantiti can be transfered as 0 quantity is available. We are using the batch as customer wanted to see batch wise rejection. If we remove reservation manually than all tracking is lost also customer is not in the favour of removing the reservation manually.

Looking for the suggestions from my friends.
Mukesh Sharma
Sign In or Register to comment.